● Project schedule management is made up of six management processes including: activity d

11 查阅

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating

参考答案:

B试题(71)分析项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity

软考高级