WithaclearSOWacontractorcompletesworkasspecified,butthebuyernotpleasedwiththeresult.Thecontractiscon

11 查阅

A、incomplete because the buyer is not pleased

B、incomplete because the specs are incorrect

C、complete because the contractor meets the terms and conditions of the contract

D、complete because the contractor is satisfied

参考答案:

C

本题题意为:按照清晰的工作说明书 (SOW),承建单位完成指定的工作,但是买方对此结果不满意。那么该合同是题中工作说明书 (SOW)是指合同中对提供的产品或服务的表述,有时候被称为需求说明书。工作说明书应足够详细,以使期望中的卖方确定是否有能力提供各事项。SOW应该包括任何所需的间接服务,比如运行情况报告或者项目后续的运作支持等。本题是考察SOW在合同的作用。承建单位按照SOW建设,是履行合同行为。建设单位的合同约束外的评价,不是制约双方约定的关键。因此,本题正确答案是C。The stages within the developement phase of the software life cycle are ( ).A、design,analysis,implementation,and testingB、analysis,design,implementation,and testingC、analysis,design,testing,and implementationD、design,analysis,testing,and implementationC